Got Light
Event Lifecycle
Timing Breakdown
Late
On Time
Early
RTP Timing Impact
Pre-Production Runway
Days From 90% Booked to RTP Due
CAD Turnaround
Days From RTP Complete to CAD Complete
Pull Lists
Shop
Days between pull sent and first day of install — under 3 days is critical
First Pull Sent — Days Before Install
Last Pull Sent — Days Before Install
Critical (<3 Days)
Tight (3–4 Days)
Good (5+ Days)
Fabrication Orders
Shop
Days before install — under 5 days is critical
First Fab Out — Days Before Install
Last Fab Out — Days Before Install
Critical (<5 Days)
Tight (5–6 Days)
Good (7+ Days)
Sub-Rentals
Shop
Days before install — 365 events with sub-rental data
First Sub-Rental Out — Days Before Install
Last Sub-Rental Out — Days Before Install
Internal Orders
Shop
Days before install — 804 events with internal order data
First Internal Out — Days Before Install
Last Internal Out — Days Before Install
Does RTP Timing Affect the Shop?
Comparing last pull lead time when RTP was late vs. early
Producer View — Shop Lead Times
Last Pull Days Prior
Salesperson View
RTP & RTN
Producer View
RTG